Dear Colleagues,
As you are probably aware, a temporary generator is currently providing power to 1050 Arastradero A&B. The generator provider, Agrekko, requires that preventive maintenance be performed every 800 hours of runtime. This service will require the generator be shut down for 4 hours.
We are scheduling with the vendor to have this preventive maintenance performed as follows:
DATE: February 3, 2026
TIME: 4:00AM to 8:00AM
IMPACT: All normal power will be off during this time. Emergency power will remain available.
SAFETY IMPACT: There will be reduced lighting and ventilation. Fume hoods may be inoperable.
Any equipment that may be adversely affected by sudden power loss should be shutdown gracefully prior to 4AM on February 2, 2026.
If you have any questions or concerns, please do not hesitate to contact me.
Thank you,
Mark Stewart
Chief Engineer – Facilities Field Services
School of Medicine