Notice of Work: Work/Electrical Shutdown to 1701 PM – Lab 262 Area
Specific Project Scope:
- General carpentry, mechanical, and electrical work required for lab modifications in Rooms 262, 262C, 262D, 262E, 263, 265.
Anticipated Schedule:
- Days #1-5: Thursday – Monday, 4/10/25 – 4/14/25 (6:00pm – 2:00am); Carpentry, minor mechanical work, and electrical rough-in.
- Day #6: Wednesday, 4/16/25 (5:00am – 7:00am); Normal/back-up power will be shut down for approx. 2 hours.
- Rooms effected: 262, 262B, and 270
- Building Impacts:
- Work to be performed off-hours (6:00pm – 2:00am), so no direct impact to users are anticipated.
- Electrical power within the noted areas shut down, see drawings below. Occupants will be responsible for the safe shut down/startup of equipment as needed to allow for the upgrades to occur.
Safety Impacts:
- No life safety impacts to the occupants are anticipated.
Contacts:
- SoM OFPM Representative: Chris Dillard, cdillard@stanford.edu, (510) 459-5470
- SoM OFPM Operations Representative: Carl Hickman, Chickman@stanfordhealthcare.org, (650) 381-4455
- SoM S&EM Representative: Naomi Takahashi, ntaka@stanford.edu, (650) 665-3734
- Contractor: Philip Bugay, philipb@hillhouseconstruction.com, (510) 342-9105