Notice of Work: Electrical work to 3174 Porter – Building Electrical/Carpentry Work
Specific Project Scope:
- Installation of unistrut and diamond plate in room 132I and outside of 132I
- Electrical work associated with changing out outlets in 161B, 132B, 132I and outside of 132I
Anticipated Schedule:
- Thursday 1/30/25 (5:00am – 9:00am) – Installation of unistrut and diamond plate
- Saturday 2/8/25 (7:00am – 3:00pm) – Pulling wires in ceiling spaces for electrical changes
- Monday 2/10/25 ( 5:00am – 7:00am) – Shutdown of panel LS1A to swap out breakers
Building Impacts:
- Shutdown of panel LS1A will turn off power to areas for 2 hours. Please review the locations of powered equipment which may be impacted by the shutdown (plans below) and contact the Project Team with any questions you may have.
Safety Impacts:
- None
Concerns:
- Please contact the project team for concerns related to this work.
Contacts:
- SoM OFPM Representative: Chris Dillard, cdillard@stanford.edu, (510) 459-5470
- SoM S&EM Representative: Naomi Takahashi, ntaka@stanford.edu, (650) 665-3734
- Contractor: Jesse Chen, jchen@gcigc.com, (858) 342-8015