UPDATE: 1050 Arastradero Electrical Repairs – Two days (5/19-5/20) 3-hours normal power shutdown to complete the electrical repair

May 12, 2026 | Activities

Good Afternoon Colleagues,
 
During today’s weekly electrical repair meeting, our contractor provided the list of activities below scheduled for this week and in the coming weeks:
 
Week of 5/4/26 – 5/8/26
    - Since Tuesday (5/5) of last week, 1050A&B building normal power is temporarily connected to CoPA utility power.
 
Week of 5/11/26 – 5/15/26
The permanent power distribution bus duct system arrived at the yard.
Installation, third-party testing, and CoPA inspections are scheduled at the end of this week. 
 
Week of 5/18/26 – 5/22/26
Shutdown building temporary utility power, connect temporary mobile generator, perform final termination of the newly installed permanent distribution bus duct system Tuesday May 19th , 4am – 7am.
IMPACT: All normal power will be off during this time. Stationary Generator emergency power will remain available.
SAFETY IMPACT: There will be reduced lighting and ventilation. Fume hoods may be inoperable.
 
Energize building utility power with CoPA Utility Transformer via Permanent Power Distribution Bus Duct System, Wednesday May 20th, 5am – 8am.   
IMPACT: All normal power will be off during this time. Stationary Generator emergency power will remain available.
SAFETY IMPACT: There will be reduced lighting and ventilation. Fume hoods may be inoperable.
CoPA performs utility transformer switching to energize the building.
Utility power restore / Project complete