Good Afternoon Colleagues,
A reminder of scheduled power shutdowns next week to complete the electrical repair of 1050 buildings’ utility power connection.
Week of 5/18/26 – 5/22/26
Shutdown building temporary utility power, connect temporary mobile generator, perform final termination of the newly installed permanent distribution bus duct system Tuesday May 19th , 4am – 7am.
IMPACT: All normal power will be off during this time. Stationary Generator emergency power will remain available.
SAFETY IMPACT: There will be reduced lighting and ventilation. Fume hoods may be inoperable.
Energize building utility power with CoPA Utility Transformer via Permanent Power Distribution Bus Duct System, Wednesday May 20th , 5am – 8am.
IMPACT: All normal power will be off during this time. Stationary Generator emergency power will remain available.
SAFETY IMPACT: There will be reduced lighting and ventilation. Fume hoods may be inoperable.
CoPA performs utility transformer switching to energize the building.
Utility power restore / Project complete
Please let me know if you have any questions or concerns.
Thank you,
Fred P. Echaluse
