Dear 1050B Arastradero Rd. Colleagues,
The Office of Facilities Planning and Management will be supporting DEMO/Removal of the existing Fulton Oiled Fired Steam Boiler at 1050B Arastradero mechanical room M103 steam plant. Our contracted vendor Commercial Air Services, will be onsite starting July 4th & 5th, 2025 at 6:00am to 4:00pm each day to complete this planned project
Project Dates: July 4th – July 5th, 2025
Time: 6:00am to 4:00pm – Daily Until Completed
What to Expect:
- The 1st floor VSC Loading dock will be blocked both days to remove large equipment.
- Pipe fitters will be entering the mechanical rooms on the 1st floors M103 Steam Plant.
- The project is expected to be completed over the weekend on July 5th, 2025.
Contracted Vendor: Commercial Air Services, LLC
Impact: Minor- The buildings loading dock will have limited access; to include, the steam plant mechanical room.
Safety Impacts: Minor – Please be aware of pipe fitters and associated equipment during this project.
Contacts: SOM Area Zone Manager: Stan Bouyea, sbouyea@stanford.edu 650-223-9689; Jorge Gutierrez, Commercial Air Service, 408-825-3391.
Please let me know if you have any questions or concerns.