Notice of Construction: 1070 Arastradero – Offices 10/14-10/15

Oct 6, 2025 | Activities

STANFORD SCHOOL OF MEDICINE Notice of Construction at 1070 Arastradero

Description:HVAC work to offices 231, 233, 235, 237, 239 & 241

Anticipated Schedule:10/14 & 10/15

Impacts: Surrounding areas will remain operational without impact. Minimal noise can be expected.

Anticipated Construction Activity:

  • Rerouting transfer air duct to the rooms
  • Relocate and reuse existing registers
  • Cap rectangular transfer duct where registers were
  • Run acoustical flex from relocated registers to existing transfer duct

FUTURE ANTICIPATED SHUTDOWNS:
None

QUESTIONS/CONCERNS:
Please do not hesitate to contact us if you have any questions or concerns. 

If there are any issues during the evening hours, please call SoM Security at  650-723-7222 and emergency personnel will be dispatch 

For Emergencies Dial 911 

TEAM CONTACT: 
Project Manager AGC: Garry Baughman, 408-508-9872
SOM Project Manager: Sally Salman, 408-386-9924 

Thanks,