Dear 1050B Arastradero Rd. Colleagues,
The Office of Facilities Planning and Management will be supporting a steam distribution upgrade at 1050B Arastradero 2nd floor steam plant. Our contracted vendor Commercial Air Services, will be onsite starting April 3th, 2025 at 6:00am to 4:00pm
Project Dates: April 3th – April 6th, 2025
Time: 6:00am to 4:00pm – Daily Until Completed
What to Expect:
- The 2nd floor Fulton Boiler Steam plant will be shut down during the schedule project on April 3rd in the evening.
- Pipe fitters will be entering the mechanical rooms on both 1st and 2nd floors on April 5th, 2025
- The project is expected to be completed over the weekend on April 6th, 2025.
Contracted Vendor: Commercial Air Services, LLC
Impact: Minor- There will be limited access to both mechanical rooms. Please be aware of pipe fitters and associated equipment during this project.
Safety Impacts: Minor
Contacts:
SOM Area Zone Manager: Stan Bouyea, sbouyea@stanford.edu 650-223-9689; Jorge Gutierrez, Commercial Air Service, 408-825-3391