Steam Distribution Upgrade – 1050 B Arastradero Rd – April 3, 2025 – April 6, 2025 at 6:00am to 4:00pm

Mar 10, 2025 | Activities

Dear 1050B Arastradero Rd. Colleagues,

The Office of Facilities Planning and Management will be supporting a steam distribution upgrade at 1050B Arastradero 2nd floor steam plant.  Our contracted vendor Commercial Air Services, will be onsite starting April 3th, 2025 at 6:00am to 4:00pm  

Project Dates: April 3th – April 6th, 2025

Time:  6:00am to 4:00pm – Daily Until Completed

What to Expect:

  • The 2nd floor Fulton Boiler Steam plant will be shut down during the schedule project on April 3rd in the evening.
  • Pipe fitters will be entering the mechanical rooms on both 1st and 2nd floors on April 5th, 2025
  • The project is expected to be completed over the weekend on April 6th, 2025.

Contracted Vendor: Commercial Air Services, LLC

Impact: Minor- There will be limited access to both mechanical rooms.  Please be aware of pipe fitters and associated equipment during this project.

Safety Impacts:  Minor

Contacts:

SOM Area Zone Manager: Stan Bouyea, sbouyea@stanford.edu  650-223-9689; Jorge Gutierrez, Commercial Air Service, 408-825-3391