UPDATE: 1050 Arastradero Electrical Repairs

Mar 24, 2026 | Activities

Dear Colleagues,

During yesterday’s weekly electrical repair meeting, our contractor provided the list of activities scheduled for this week and in the coming weeks:

Week of 3/23/26 – 3/27/26

  • Mandrel Test and inspection of newly installed underground conduits.
  • Pour concrete for duct bank.
  • Backfill open trenches.

Week of 3/30/26 – 4/3/26

  • CoPA Mandrel Inspection.
  • Prep / Form / Rebar for concrete pads.
  • CEL special inspection & CoPA inspection of rebar.
  • Pour concrete pad and sample testing.

Week of 4/6/26 – 4/10/26

  • Temporary Generator Service scheduled on Tuesday (4/7) from 4am to 8am.
  • Transformer grounding inspection.
  • Set Precast Transformer pad.

Week of 4/13/26 – 4/17/26

  • CoPA installation of transformer, primary cables & connections.

Due to long lead time of non-stock materials required to complete the repairs, the expected completion date at this time is on 5/13/26.

Please let me know if you have any questions or concerns.

Thank you,

Fred P. Echaluse
Facilities Engineer