Dear Colleagues,
During yesterday’s weekly electrical repair meeting, our contractor provided the list of activities scheduled for this week and in the coming weeks:
Week of 3/23/26 – 3/27/26
- Mandrel Test and inspection of newly installed underground conduits.
- Pour concrete for duct bank.
- Backfill open trenches.
Week of 3/30/26 – 4/3/26
- CoPA Mandrel Inspection.
- Prep / Form / Rebar for concrete pads.
- CEL special inspection & CoPA inspection of rebar.
- Pour concrete pad and sample testing.
Week of 4/6/26 – 4/10/26
- Temporary Generator Service scheduled on Tuesday (4/7) from 4am to 8am.
- Transformer grounding inspection.
- Set Precast Transformer pad.
Week of 4/13/26 – 4/17/26
- CoPA installation of transformer, primary cables & connections.
Due to long lead time of non-stock materials required to complete the repairs, the expected completion date at this time is on 5/13/26.
Please let me know if you have any questions or concerns.
Thank you,
Fred P. Echaluse
Facilities Engineer